What Is Burn Rate?
Filed in Project Cost Management, March 28, 2010, 4:30 amThe burn rate is a project management metric assessing the performance of the project with respect to the budget. A burn rate bigger than 1 indicates that the project is burning money faster than it should, a burn rate less than 1 indicates that the project is burning money slower than it originally planned. Burn Rate = 1/CPI = AC/EV.